Feedback requested on U.P. Defence and Aerospace Policy and Defence Corridor Selection of PR, Design & Creative Agency for Branding & Promotion of UP Appointment of Event Management Agency for UPIS-2018 Civil Aviation Promotion Policy of UP 2017 Industrial Investment and Employment Promotion Policy of Uttar Pradesh 2017 'Samadhan Divas' started by State Level Udyog Bandhu every First & Third Thursday Help Line implemented for resolution of issues of entrepreneurs, businessmen and investors of ...... Formats for Mega Projects Draft Property Management (Industrial Land) Rules & Regulations, 2014 To encourage mega projects in the state INDUSTRIAL ASSETS AVAILABLE FOR SALE Entry Strategies for Foreign Investors NRI Cell at Udyog Bandhu Vacant Land with Govt. Deptt. Restructuring of State, Division & District level Committies of Udyog Bandhu Strengthening of Udyog Bandhu Golden Card Scheme

 

ONGOING PPP PROJECTS-UP STATE HIGHWAYS AUTHORITY(UPSHA)

 

 

1.    Upgradation of State Highways

 

S.No.

Name of Roads

Length in Km.

Estimated cost (In Rs. Cr.)

Status

1.

Delhi-Saharanpur-Yamunotri Road (SH57)

206.089

1718.35

M/s SEW - Prasad Consortium Infrastructure Limited, Hyderabad selected as a developer. Concession agreement signed on 01.08.2011.Independent Engineer selected, agreement signed on 28.02.2012. Developer has started work, date of completion of project is 16.09.2014.

2.

Bareilly-Almora-Bagheshwar Road (SH-37)

54

354.07

M/s PNC Infratech Ltd., Agra selected as developer. Concession agreement signed on 01.08.2011. Independent Engineer selected, agreement signed on 08.02.2012. Forest Clearance NOC has been obtained from GOI. Date of completion of project is 18.08.2015.

3.

Varanasi-Shaktinagar Road(SH-5A)

115

1211.96

M/s APCO Chetak - Patel Ltd., Lucknow selected as a developer. Letter of award issued on 15.11.2011. Concession agreement signed on 08.12.2011. Forest clearance NOC has been obtained from GOI. Date of completion of project is 18.09.2015. 

4.

Akbarpur-Tanda-Jaunpur-Mirzapur-Dudhi Road (SH-5)

207.47

1832.00

Consultant selected. RFQ for selection of developer has been issued on 25.03.2013. Bid submission date is 13.05.2013. 

5.

Sahjahanpur-Hardoi-Lucknow Road (SH-25)

162

1039.83

Consultant selected,  proposal for VGF submitted to GOI on 31.01.2011. RFQ for selection of developer has been issued on 25.03.2013. Bid submission date is 13.05.2013.  

6.

Meerut-Karnal Road (SH-82)

87.155

583.23

M/s Abhijeet Road Ltd., Nagpur selected as developer. Concession agreement signed on 08.12.2011. Further M/s CMEC consulting engineering has been selected as independent engineer. Agreement signed on 20.09.2012. Expected date of completion of project is 01.04.2015.

7.

Gorakhpur-Maharajganj Road (SH-81)

53.160

159

Consultant selected, feasibility report has been prepared by the consultant. RFQ for selection of developer has been issued on 25.03.2013. Bid submission date is 13.05.2013.  

8.

Basti-Mehndwal-Kaptanganj-Tamkuhi Road (SH-64)

166.12

303.05

Consultant selected, feasibility report has been prepared by the consultant. Proposal for VGF submitted to GOI on 20.05.2011. RFQ for selection of developer has been issued on 25.03.2013. Bid submission date is 13.05.2013. 

9.

Moradabad-Chandausi-Badaun Road (SH-43)

164.17

656

Consultant selected, feasibility report has been prepared by the consultant is being examined. Proposal for VGF Under preparation.

10.

Farenda-Naugarh-Barhni-Tulsipur-Balrampur-Gonda Road (SH-1-A)

230

690

Consultant selected, feasibility report has been prepared by the consultant is being examined. Proposal for VGF under preparation.

11.

Garh-Meerut-Baghpat-Sonipat Road (SH-14)

90.42

900

Consultant selected, feasibility report has been prepared by the consultant is being examined. In the BEC meeting dated 25.04.2011, it has been decided that clarification should be shout out regarding land near Meerut Bye Pass before releasing the RFQ. Proposal for VGF under preparation.

12.

Etawah-Mainpuri (SH 83)

52.82

370

Consultant selected. Feasibility report has been prepared by the consultant. RFQ is to be issued for selection of developer.

13.

Aligarh Mathura (SH-80)

38.96

300

Consultant selected. Feasibility report has been repared by the consultant. RFQ for selection of developer has been issued on 25.03.2013. Bid submission date is 13.05.2013.  

14.

Etah Tundla (SH-31)

57.16

400

Consultant selected. Feasibility report has been prepared by the consultant. RFQ for selection of developer has been issued on 25.03.2013. Bid submission date is 13.05.2013. 

15.

Etah Shikohabad Marg (SH-85)

52.5

368

Consultant selected. Feasibility report has been repared by the consultant. RFQ for selection of developer has been issued on 25.03.2013. Bid submission date is 13.05.2013.  

16.

Varanasi Bhadohi-Gopiganj (SH-87)

60.12

325

Consultant selected. Feasibility report has been prepared by the consultant. RFQ for selection of developer has been issued on 25.03.2013. Bid submission date is 13.05.2013. 

17.

Tarighat - Bara Road (SH-99)

40

340

Consultant selected. Feasibility report has been repared by the consultant. RFQ for selection of developer has been issued on 25.03.2013. Bid submission date is 13.05.2013.  

18.

Kalwari-Barhalganj-Lal-Ghuthni (SH-72)

189.82

580

Consultant selected Feasibility report as been prepared by the consultant. RFQ is to be issued.

19.

Muzaffarnagar Saharanpur via Deoband (SH-59)

52.70

369

M/s Krishna Techno committee (P) Ltd. has selected as Consultant, agreement signed on 05.12.2012. RFQ for selection of developer has been issued on 25.03.2013. Bid submission date is 13.05.2013.  

20.

Bahraich-Gonda-Faizabad Road (SH-30)

190.00

-

Consultant has been selected, Feasibility report is being prepared by the consultant.

21.

Bareilly-Badaun-Kasganj-Hathras-Marg (SH-33)

232.00

-

Consultant has been selected, Feasibility report is being prepared by the consultant.

22.

Bharwari-Manjhanpur-Chitrakoot Road (SH-94 & MDR-26)

78.00

-

Consultant has been selected, Feasibility report is being prepared by the consultant.

23.

Sitapur-Lakhimpur-Kheri Marg (SH-21)

45.00

-

RFQ cum RFP issued for selection of technical bids opened on 11.03.2013, evaluation is being made.

24.

Pilibhit-Farrukhabad-Waiver Marg (SH-29)

214.00

-

Consultant has been selected, Feasibility report is being prepared by the consultant.

25.

Windhamganj-Kon-Kota-Chopan Road (ODR)

59.34

-

RFQ cum RFP issued for selection of technical bid opened on 11.03.2013, evaluation is being made.

26.

Nitchlol-Thotibadi (2 Lane)

160.00

-

Necessary steps are being taken for selection of consultant.

 

Total

13477.83

12499.49

 

 

 

U.P. State Highway Authority


4th Floor, Mandi Bhawan, Vibhuti Khand,Gomti Nagar
Lucknow _ 226 010
Tel#: +91-522-4150377/4150301
Fax ; +91-522-4150377
E-mail - info@upsha.in
Website: http://upsha.in
 

 

 

 

 

Infrastructure & Industrial Development Department

Government of Uttar Pradesh, 4th Floor,

Shri Lal Bahadur Shashtri Bhawan,

Sarojini Naidu Marg,

Lucknow- 226 001. (U.P.)


Phone No:- 91-522-2238283/2239530

Fax No:- 91-522-2238255

Email :- iidcup.84@gmail.com

Visitor Online: 153      Visited Till Date: 7517041     
All rights reserved by: Udyog Bandhu Best viewed in Mozilla-Firefox and Internet Explorer 7 and above Maintained & Supported by: APV India Pvt. Ltd.