30. Preparation of Detailed Project Report (DPR)/Techno Economic Feasibility Report (TEFR) by the consultant
31. Preparation of report on Environmental Impact Assessment (EIA)/ Social Impact Assessment (SIA) by the consultant depending on complexity of the project
32. Approval by BEC on DPR/TEFR report as put up by the department
33. Preparation of RFQ (indicating project details, last date of submission, eligibility criteria on technical and Financial parameters, Methodology of evaluation, instruction to applicants, fee, sweetener etc.) by the consultant in consultation with the Department
34. In principle consent on RFQ from BEC under the chairmanship of IIDC (put up by the department)
35. Issuance/Publication of RFQ by the Concerned Department including Displaying RFQ on website by the Department (Time limit normally 21 days, may be extended as per demand of the bidders in pre bid meet or otherwise)
36. Organizing Pre-bid meeting by the Department
37. Amendment of RFQ based on feedback received from prospective bidders, if required
38. Approval of modified RFQ by BEC (under chairmanship of IIDC)
39. Issuance of modified RFQ by department
40. Organizing subsequent Pre-bid meetings by the Department, if need be
41. Approval of further modification in RFQ by BEC, if need be
42. Issuance of modified RFQ by department
43. Receipt of RFQ proposals by the department
44. Opening of bids and checking responsiveness of bidders by BEC
45. Short-listing & Evaluation of prospective bidders on Technical & financial criteria by BEC
46. Selection of qualified bidders by BEC to whom RFP is to be issued
47. Preparation of RFP {including Letter of Invitation (LOI), Instructions to Developer (ITD), Draft Project Report (DPR), Bid Parameters last date of submission, fee, Draft Concession Agreement etc.} by the consultant
48. Examination & in principle approval of RFP/DCA (Draft Concession Agreement) by BEC (put up by the department)
49. Issuance/Publication of RFP by the Concerned Department including Displaying on website by the Department (Time limit normally 28 days but not less than 21 days; may be extended as per demand of the bidders in prebid meet or otherwise)
50. Organizing Pre-bid meeting on RFP/DCA by the Department
51. Amendment of RFP/DCA based on feedback received from prospective bidders, if required
52. Approval of modified RFP/DCA by BEC (under chairmanship of IIDC)
53. Issuance of modified RFP by department
54. Organizing subsequent Pre-bid meetings by the Department, if need be
55. Examination & in principle approval of modified RFP/DCA by BEC, if need be
56. Issuance of modified RFP by department
57. Preparation of Draft Cabinet Note on modified /final RFP/DCA (alongwith RFQ, if required) by the concerned Department for approval
58. Sending Cabinet Note to IDD for finalization and taking approval on modified/final RFP/DCA (along with RFQ, if required) of Cabinet
59. Approval of Cabinet on RFP/DCA (along with RFQ, as the case may be)
60. Receipt of RFP proposals by the department
61. Opening of bids and checking responsiveness of bidders by BEC
62. Evaluation of bids by BEC
63. (a) Recommendation of developer by BEC (under the chairmanship of IIDC) for projects up to Rs. 1000 Cr. for final approval from the Cabinet
OR
b) Recommendation of developer by Committee of Secretaries (under the chairmanship of CS) for projects beyond Rs. 1000 Cr. for final approval from the Cabinet
64. Preparation of Draft Cabinet Note on selection of Developer by concerned Department for approval
65. Sending Cabinet Note to IDD for finalization and taking approval on selection of Developer of Cabinet
66. Approval for selection of developer by the Cabinet
67. Award of contract to the selected developer by the concerned Department
68. Signing of concessionaire agreement between the Developer & Deptt.
|